Credit:

Rediscovery and Renewal

The developments in the 1960s and 1970s, although controversial at the time, were popular in use at least while they were still new.

Park usage dwindled by the start of the 21st century as facilities became rundown and its safety was called into question after some serious crimes.  Confidence was slow to return and initially depended on small steps which included a new play park in 2003 and the Family Tree Scheme which started in 2004.  In 2012, the Life Centre opened, not only replacing the former swimming pool and Mayflower leisure centre but also leading to a better arrangement of buildings and use of space in the area.  

In 2017, Plymouth City Council embarked on a further package of improvements that included a new café, new tennis courts, new and improved sports pitches, new play area, skate park extension, a sustainable drainage scheme, path improvements and tackling deferred maintenance.  A major milestone was reached in 2019 when the park achieved its first ‘Green Flag’ award.  

Looking ahead, attention is turning to the park’s northern quadrant and to giving Pounds House a sustainable future, whilst consolidating recent achievements to retain the park’s ‘Green Flag’ status.    

  • An Evolving Park – Plans and Reports
  • Adventure playground
    Play facilities in Central Park took a major step forward in 2003 when the Seven Continents adventure playground opened on a new site, south west of the clock tower.  Before then there was a small traditional playground on the south side of Britannia Way between the swimming pool and the clock tower, which had been… Read more: Adventure playground
  • Family Tree Scheme
    In 2003 the conservation charity, International Tree Foundation, was looking to extend its Family Tree Scheme to more places.  At the same time, Plymouth City Council wanted a better use for ‘Lane End’ – the field next to Cottage Field between Gilbert Lane and Jubilee Row – and decided to make it available.  Football and… Read more: Family Tree Scheme
  • Orienteering comes to Central Park
    Work to design and install a permanent orienteering course was completed between 2003 and 2004.  Much of the surveying and mapping was done by volunteers with the Devon Orienteering Club whilst Plymouth City Council installed the marker posts and an interpretation panel. Subsequent revisions led to this course map in 2013.  Orienteering is a combination… Read more: Orienteering comes to Central Park
  • Successor Skate Parks
    There had been an extensive, privately-run skate park in Zoo Field which was demolished in 1981.  In July 2004 a new, public skate park was built on the present site south of Britannia Way near the Alma Road entrance.  This too was demolished and replaced in late 2011 with an improved design by the specialist… Read more: Successor Skate Parks
  • Plymouth Life Centre
    Whatever their merits as sporting facilities, the swimming pool and Mayflower centre had little connection with the park.  The large buildings were poorly situated and intruded on vistas whilst their drab elevations made an ugly backdrop for a green space setting. As the buildings deteriorated and maintenance burdens increased, replacement options started to be investigated… Read more: Plymouth Life Centre
  • Trees planted on Jubilee Row
    Ruth Heaton (left), Jean Waterfield (middle) and Joan Hassall (right) were among those who as schoolchildren took part in planting trees on Coronation Avenue in 1937.  Seventy-five years later, they joined the Lord Mayor in planting the final tree to commemorate the Diamond Jubilee of Queen Elizabeth II in 2012.  With the new trees grouped… Read more: Trees planted on Jubilee Row
  • Events Field
    Building the Life Centre generated huge quantities of earth and rubble, not only from its deep foundations but also from the demolition of the old swimming pool.  In addition, a large heap of spoil had been deposited at the top of Zoo Field in 2001 when three sides of Argyle’s stadium were replaced with the… Read more: Events Field
  • Orchard Path
    In the recession that followed the banking crash in 2008, people were attracted to growing their own food and, by 2011, more than a thousand were on the waiting list for one of Plymouth’s 1394 allotment plots.   Plymouth City Council started to bring redundant plots back into use and, in 2014, approved plans to… Read more: Orchard Path
  • The Sports Plateau
    The playing fields on the western side of Discovery Way had long suffered from poor drainage and were frequently unplayable in wet weather.  There was also a marked fall across the field which exceeded the sports’ governing bodies guidelines for pitch slopes.  The improvements, started in 2018, included a level adjustment whereby the topsoil was… Read more: The Sports Plateau
  • Tennis Courts
    When the park opened in 1931, there were eight hard tennis courts where the Life Centre Field is today.  The courts were removed to make way for the Mayflower Leisure Centre in 1970 and its subsequent extensions.  From 1978 until July 2019, when four new courts were opened, no tennis could be played in Central… Read more: Tennis Courts
  • The Meadow Café
    The Meadow Café opened on 26th July 2019.  It was built next to the clock tower roundabout on the site of the changing rooms and public toilets which had been demolished circa 2002.   The café brought a much-wanted facility to the park.  Adults could comfortably keep an eye on their children in the nearby playground… Read more: The Meadow Café
  • Community Sports Hub
    By 2015, the bowling pavilion was almost 25 years old and in need of refurbishment.  Its facilities did not meet modern standards while, outside, its walls frequently attracted graffiti. Additionally, it was used only by bowling teams in the summer months although it had the capacity to accommodate many other uses throughout the year.   As… Read more: Community Sports Hub
  • Sustainable Drainage System
    The sustainable drainage system, or ponds project as it became known, was the last development funded in the 2017 improvements package.  Unlike other work which improved individual facilities, the scheme involved wide-scale landscape changes along a pivotal axis of the park.   The scheme had four main elements: The main design drivers were to reduce… Read more: Sustainable Drainage System